East Ardsley, Leeds
Scheme Outline: Remediation for a new 250 unit residential development on a former rail sidings bounded by motorway and East Coast Main Rail Line. The principle operation was to remediate the site and construct building platforms.
Client: Miller Homes.
Value: £450,000.
Additional Details:
- Excavation and recycling of 47,000 tonne of ash contamination - all of which was re-used in concrete block manufacture.
- Reduction in logistics was made by utilising the ash export vehicles to also import the stone fill.
- Reduction in disposal costs by 70%.
- 160,000 tonne of excavated material was re-engineered into validated platform levels.
- Estimated overall savings on the remediation cost was 30% - compared to using traditional techniques.
- The remediation solution produced a cost plan for the client that confirmed the site to be a more than viable investment.